Current Public Works Projects

For more information on any SWD projects, please contact the District Manager at 360-683-3905 x 3

FAWNWOOD LIFT STATION PURCHASE & INSTALLATION

Project Description:

Purchase and installation of a Smith & Loveless factory-built Everlast Series 1000 pump station complete with hinged fiberglass housing and structural steel base suitable for installation on top of a 6’-0” inside-diameter wet well opening. Station is provided with 4” flanged suction connections and a 4” plain-end discharge connection with compression coupling.

The work will be performed by Utilities Services Co., Inc.  The contract in the amount of $105,600.00 was awarded on 11-1-23. 

Location where the bid quotations for this contract are available for public inspection:  District Office at 5762 Woodcock Road, Sequim, WA  98382

Project is being funded by the SunLand community through annual water and sewer fees.

Serving SunLand with Clean Water

SunLand Water District

5762 Woodcock Road,
Sequim, WA  98382

Office hours are 9-1
Monday through Friday

Tim Berger, District Manager

Phone: (360) 683-3905

Fax: (360) 683-3324

Our Location